Chapter 2  Results of Technical Cooperation Project



            2.1.2 Inputs by Vietnamese side


               The following inputs have been provided by the Vietnamese side to the Project as planned described
                                   th
            in RD (signed on Nov. 16 , 2015).
             Components                                            Inputs
                                 Project Director: 1 person (Vice Rector of CTU)
                                 Project Manager: 1 person (Vice Rector of CTU)
                                 Other counterpart personnel and staff members related to the Project:
                                 A total of 213 persons. The breakdown is as follows:
                                    a)  11 members of Rector Board
                                    b)  36 members of PMU (including three colleges of CoA, CAF and CENRes)

             Allocation of          c)  17 members of Supporting Units
             Counterparts           d)  40 leaders of the Joint Research Programs

                                    e)  21 co-lecturers and managing staff for the new master’s programs

                                    f)  13 persons of the New Master’s Programs Committee
                                    g)  08 task force members for Regulations & Ethics on Animal Experiment
                                    h)  23 task force members for Laboratory Regulations and Safety
                                    i)   07 committee members for Scheme Drafting for Center of Common Use

                                        Equipment
                                    j)   37 committee and task force members for SDMD-Outlook 2045

                                                                                             (See Annex 2.3)
                                 a) Suitable office space with necessary equipment, electricity, telephone line
                                 internet access, etc.
             Facility and
             Equipment           b) Supply or replacement of machinery, equipment, instruments, vehicles, tools,
                                 spare parts and any other materials necessary for the implementation of the
                                 Project other than the equipment provided by JICA.
                                 a) Running expenses necessary for the implementation of the Project.
             Local cost          b) Expenses necessary for transportation of the equipment within Viet
                                 Nam referred to above 2.1.1 as well as for the installation, operation and
                                 maintenance.
             Others              a) Credentials or identification cards.

                                 b) Available data (including maps and photographs) and information related to
                                 the Project.
            2.2 Outputs



               Performances of the Project activities are described below. The activities of each Output are listed
            according to the PDM. Planned schedule of each activity shown below is at the beginning of the Project
                                                                                            th
            which is stated in the Project Document (Decision No. 1820/QD-BGDDT on March 27 , 2015).