Page 110 - Technical Cooperation Project for Building Capacity for Can Tho University...
P. 110

Chapter 4  Results of Joint Review



               The progress of the construction of the new facilities and procurement of equipment has significantly
            been affecting some activities of the output 3 of the Project.

               These two Projects have functioned effectively in a complementary manner and have had synergistic
            effects, as originally expected.
             3) Factors contributing to the achievement of the Project purpose


               a) Effective and functional Project implementing structure in CTU (PMU, assignment of key members
            in three core colleges and supporting units, organizing relevant task forces and committees);
               b) Assignment of responsible and competent staff for the above units and favorable working
            atmosphere for smooth communication with the Project team;
               c) Good collaboration and partnership with local governments, institutions and companies in
            implementing Joint Research Programs;

               d) Support by many Japanese collaborators in JSUC for Joint Research and the New Master’s Program
            from the initial stage of the Project;

               e) As shown in III. 2 “The results of questionnaire survey”, implementation of 40 Joint Research
            Programs has highly contributed to enhancing research and education capacity. It has also given
            positive influence on awareness of safety practices, team discussion atmosphere, and environmental
            consciousness.


            4.1.4 Efficiency

               Efficiency of the Project cannot be judged to be high because many activities and programs have
            been restricted by the COVID-19 pandemic since February 2020.

            1) Project Cost on the Japanese side


               The Project has been extended for 9 months until December 14th, 2021 because of the COVID-19
            pandemic. The budget that could not be spent due to COVID-19 was allocated to the Project operation
            cost during the extended period and partly to purchasing online equipment for research, lectures and
            seminars. Thus, the total Project cost on the Japanese side is expected to be within the original budget
            as originally planned.
            2) Project period

               As described above, the Project was extended for 9 months until December 14th, 2021 to compensate
            for the delay of the planned Project activities due to COVID-19. Therefore, the amount and timing of
            inputs were relatively appropriate because of the extension of 9 months.
            3) Project activities affected under the COVID-19 pandemic

               The COVID-19 has negatively impacted the Project activities since February 2020 (as of July 2021).
            The followings are the main activities affected by COVID-19:

               a) Long-term experts: Two Japanese long-term experts (Chief advisor and academic advisor) had
            evacuated to Japan from April to August 2020 (five months).





                                                                                                            83
   105   106   107   108   109   110   111   112   113   114   115